Airports vs Buildings

Plans for building developments can, and do, receive objections from airports. Invariably, these relate to flight safety, which gives the objection a loud voice in the ear of the planning authority. This article presents an overview of what to expect and what to do for some of the more common concerns.

Too tall

Structures around airports have the potential to present a collision hazard. In order to manage this risk, airports typically require physical safeguarding assessments for proposed obstructions in their vicinity. Usually these assessments will consider the structure against a series of imaginary surfaces that extend in three dimensions from the airport’s runways. In the United Kingdom, these surfaces are defined within the UK Civil Aviation Publication ‘CAP 168 – Licensing of Aerodromes’ (more information can be found here or on the CAA’s website). This method of physical safeguarding is based on the International Civil Aviation Organisation (ICAO) guidance and is adopted by many authorities around the world.

The figure below shows a hypothetical obstruction located beneath the Outer Horizontal Surface at Gatwick Airport.

Obstruction Assessment / Physical Safeguarding Assessment chartFigure 1: Physical safeguarding assessment

Too close

Large buildings that are close to an airport have a greater chance of receiving an objection than obstructions at greater distances. Distance alone is not the only factor. The building location relative to the runway alignment, for example, comes into play but broadly speaking concerns diminish with distance.

At distances of around 20 km, any development will be clear of the Obstacle Limitation Surfaces and concerns over collision risk become much less likely.

Radar

Radar is used by airports and air navigation service providers (ANSPs) to monitor air traffic over large distances in all weather conditions.

UK Radar Installation - by Pager PowerFigure 2: Radar installation (UK)

There are many kinds of radar, however all of them work by emitting electromagnetic signals, which are returned via an aircraft [1]. Large buildings near radar systems can cause interference by blocking or reflecting the inbound and/or outbound radar signals.

Objections to building developments can be received from radar operators. Such objections are more likely for developments within 20 km of a radar system, however there is no formal limit.

More information regarding radar interference from buildings can be found here.

Other issues

Airports operate a variety of other navigation aids, such as Instrument Landing Systems and radio beacons. A review of all these systems and associated impacts of buildings is not presented here. Suffice it to say that building developments within a few kilometres of airports may well receive an objection due to potential interference with radio navigation aids.

Solutions

Individual cases must be assessed on their merits. There is no ‘catch all’ solution for airports that object to buildings. However, in general terms, solutions often include:

  • Detailed assessment to quantify any potential effects – this may demonstrate that the resulting impact will be imperceptible or tolerable.
  • Changes to the building height or shape – lower buildings typically have a lesser impact than taller ones. The shape of the building affects its reflective properties.
  • Technical mitigation – for particular radar types (secondary surveillance radar (SSR)) it is possible to program known reflectors into the system in order to suppress technical effects.

What to do

It is worth establishing early on what the potential aviation constraints might be. Developers should establish whether:

  • There is an airport within 20 km of the proposed building.
  • There is a radar system within 20 km of the proposed building.
  • The proposed development is significantly taller than other buildings surrounding it.

Where potential concerns are identified, consultation with the relevant stakeholders should be progressed.

If an objection is received, a detailed assessment to quantify the potential impact should be undertaken.

If an operationally significant impact is predicted, mitigation options can be explored.

Can Pager Power help?

Pager Power has experience in assessing and resolving aviation concerns with buildings. If you have a project that is being affected by similar concerns, then call +44 (0) 1787 319001 and speak with Pager Power’s technical team to receive a proposal.

Footnotes

[1] Non-cooperative systems rely on reflection of the signal by the aircraft. Cooperative systems rely on an ‘interrogation and response’, requiring aircraft to be fitted with transponders.

post contents

About the Author: Mike

Since forming Pager Power in 1997, Mike has established himself a leading authority within the field of aviation studies. Mike is also a qualified Microsoft Certified Application Developer and a member of the Institute of Electrical Engineers (MIEE) and a Chartered Engineer (CEng). More articles by mike

Latest News

Telecoms guidance

Free Guidance:

Download the Developers’ Guide to Assessing Telecoms Infrastructure Risks for Wind and Building Projects

Fill in your details below to receive regular industry know-how by email and get access to our best practice methodology, developed over 20 years and 1000+ assessments. The guide will help your wind or building development avoid delays and stay compliant with telecoms planning guidance.

Building developers checklist

Free Guidance:

Get Your Building Development Approved Faster.

Free Planning Checklist Covering Aviation, Telecommunications, Daylight Sunlight And More!

Download our checklist based on over 20 years’ experience to ensure your development is not delayed during the planning process.

Sign up for our industry newsletter and receive our Building Developer Planning Checklist. Just fill out the form below and we’ll send it directly to you.

Free Guidance:

Onshore Wind & Aviation

7 things developers need to know

Understand the key aviation issues facing the future of onshore wind across the world.

Sign up for our industry newsletter and receive our Onshore Wind & Aviation guidance today. Just fill out the form below and we’ll send it directly to you.

TAKE THE FIRST STEP TODAY

Fill in your details and one of our team will contact you to discuss your options

and help you with the best solution

YOU CAN MAKE AN ENQUIRY HERE

To upload, drag a file here
Glint and Glare Guidance

Free Guidance:

Understand the basics of Glint And Glare and the methodology behind the assessment

Download the industry standard assessment methodology, defined from over 10 years’ experience and more than 1,800 assessments. The guide covers the process for assessing roads, dwellings, rail and aviation activity.

Sign up for our industry newsletter and receive the 4th edition of our Glint and Glare Guidance today. Just fill out the form below and we’ll send it to you directly.

Go to Top